LINCOLN PIPESTONE RURAL WATER SYSTEM
East Highway 14, P.O. Box 188, Lake Benton, MN
56149
(507)368-4248 fax (507)368-4573 email: lprw@itctel.com
MEETING MINUTES
November 25, 2002
The regular scheduled meeting of the
Lincoln Pipestone Rural Water (LPRW) System Board of Commissioners was held at
the LPRW office in Lake Benton on Monday, November 25, 2002 starting at 10:00
a.m. Chairman Frank Engels called the meeting to order with Commissioners
Roger Gilliland, Ken Buysse, Jerry Lonneman, Charlie Simonson, Leonard Swenson,
Bill Ufkin, Henry Van Dyke, and Rod Spronk present. Commissioner Joe Weber was
absent. Also present were LPRW
Attorney, Dan McDonald; DGR Engineers, John Madden and Darin Schriever; Field Superintendent, Don Drietz;
Director of Operations, Don Evers; and Director of Finance and Administration,
Dennis Healy.
Agenda:
The Agenda was approved as presented.
Minutes:
M/S/P Van Dyke/Swenson to approve the minutes of the October 28, 2002
Regular Board meeting. M/S/P Ufkin/Lonneman
to approve the minutes and the recommendations of the November 19, 2002 Personnel
Committee meeting. M/S/P Ufkin/Simonson to approve the minutes and the 2003
Budget and Capital Improvement Program recommendation of the November 19, 2002 Budget
& Finance Committee meeting. M/S/P Buysse/Swenson to approve the minutes
and the recommendations of the November 19, 2002 Executive Committee meeting.
Treasurer's Report:
M/S/P Swenson/Van Dyke to approve the Treasurer's Report as presented.
Bills:
M/S/P Swenson/Simonson (Engels abstained) to approve the following bills
for payment:
·
DeWild
Grant Reckert and Associates Company: Minneota Tower #27 = $2,700.29; NE Phase
#24 = $11,840.51; Lynd Area #23 = $3,444.80; General Services #20 = $785.00
·
McDonald,
Gudmestad & Schramel: NE Phase = $300.00; General Legal Services = $790.63
·
Engineering
America, Inc.: Lynd Standpipe & Booster-Pay Estimate #5 = $11,868.35
·
Underground
Developers, Inc.: Lynd Schedule 1B Pipeline – Pay Estimate #2 = $49,302.05
·
Eatherly
Constructors, Inc.: NE Phase Schedule 1B Mainline-Pay Estimate #1 = $295,323.72
·
Carstensen
Contracting, Inc.: Schedule 1A User Additions-Pay Estimate #3 = $151,185.26
·
Winter
Brothers Underground: Lynd Schedule 1A Pipeline = $31,889.54
·
Lewis &
Clark Rural Water System: October-December 2002 quarterly fee = $14,117.00
·
Energy
Alternatives: Burr and Verdi Standby Generators = $95,835.79
·
US Bank-1998
Refunding Bonds = $32,662.50; 1998 Series B Refunding Bond = $280,937.50
Attorney’s Report:
LPRW Attorney, Dan McDonald reported on the following items:
·
McDonald reported
that the assessments for hookups outside the Burr Service Area are being
processed for assessment this year.
·
The amended
Lewis & Clark Rural Water System agreement is being further revised, and it
will be available for Board action at a future meeting.
·
The “Joint
Statement of Policy for Provision of Water Service In and Around the City of
Marshall” was reviewed and discussed.
M/S/P Van Dyke/Lonneman to approve the “Joint Statement of Policy for
Provision of Water Service In and Around the City of Marshall” and to forward
it to Marshall Municipal Utilities for their action.
Burr Exploration: LTP Enterprises is prepared to begin work on Burr Well #8 in the
near future, and we may want to have them install a second test well in the
Well 8 aquifer and Well 6 aquifer so we have backup wells in each aquifer. Liesch Associates have estimated that the
cost of this work will be approximately $35,017.00. M/S/P Lonneman/Swenson to authorize Evers and Healy to approve
proceeding with this work if Well #8 looks promising and USDA-RD will approve a
change order to the existing contract.
Wellhead Protection:
Healy reported that there are no new wellhead issues.
Regional Water Supply:
Liesch Associates has reported that the work at the City of Adrian well
field looks promising. We received a
letter from the City of Dawson indicating that they will be providing us with a
water sales proposal in the near future.
Edgerton has not provided any new information.
Water Service Requests: LPRW
staff and Board members have met with the Cities of Hanley Falls, Lismore and
Rushmore to discuss water service.
Hanley Falls has decided to build their own water treatment plant and
will not be connecting to LPRW. Lismore
and Rushmore may be interested, but we informed them that LPRW needs to have
distribution problems solved in their area before we can commit to providing
water service. Discussions with Lismore
and Rushmore will continue, but we also need to consider requests for water
service from rural residents.
Director of Operations
Report: Don Evers reported on the following items:
· Evers provided an update on Lewis &
Clark progress, and reported that new agreements are being reviewed.
· The Verdi and Burr standby generators are
to be connected on December 4th and 5th.
· The Erickson and Clairemont hookups should
be completed soon because they decided to pay for the extra footage required
when no additional hookups could be found in the area.
· The Lynd Tower and Booster SCADA is being
installed.
· A quote from EFI for $36,373 to upgrade
the Leota booster station pumps was presented for Board action. M/S/P Ufkin/Buysse to authorize EFI to
proceed with the Leota booster station pump upgrade at a cost of $36,373.
Engineer’s Report: Darin Schriever reported on the following items:
• Lynd Project:
Winter Brothers Underground has completed all work and Change Order #2
to decrease the contract by $513.15 was presented along with the Final Pay
Estimate. M/S/P Lonneman/Van Dyke to
approve Change Order #2 and to make the Final Payment contingent on completion
of Change Order #2 by Winter Brothers. Engineering
America Inc. is nearly done with the Lynd Standpipe and Booster project. Underground Developers Inc. is making good
progress on the Schedule 1B Pipeline work, but the railroad is requiring longer
bores than those bid so Change Order #2 to increase the contract by $22,950.00
was presented. M/S/P Buysse/Swenson to
approve Change Order #2 to increase the Underground Developers, Inc. contract
by $22,950.00. U.S. Filter is providing
the Lynd SCADA and Vlaminck Electric is doing the electrical hookup.
• Minneota Tower & Booster Project:
The Minneota Tower & Booster project is progressing. Caldwell Tanks has decided that they will
not start on the steel work until spring.
Change Order #1 to increase the Caldwell contract by $2,675.00 was
presented. M/S/P Swenson/Simonson to
approve Change Order #1 to increase the Caldwell contract by $2,675.00. KHC shop drawings are being reviewed, and
the SCADA system has been ordered.
• North Internal Users Project:
The Internal Users Expansion is proceeding on schedule, and Change Order
#3 to increase the Carstensen Contracting, Inc. Schedule 1A User Additions
contract by $4,940.00 was presented.
M/S/P Ufkin/Swenson to approve Change Order #3 to increase the
Carstensen Contracting, Inc. Schedule 1A User Additions contract by $4,940.00.
• Northeast Phase Expansion Project: Eatherly Constructors, Inc. is making
good progress, and Change Order #1 to increase the Schedule 1B Mainline
contract by $3,259.20 was presented.
M/S/P Lonneman/Buysse to approve Change Order #1 to increase the Eatherly
Constructors, Inc. Schedule 1B Mainline contract by $3,259.20.
• The
Green Valley booster station is being designed, and billing of new users was
discussed.
Director of Finance and
Administration Report:
·
The
Towerlink America agreement was tabled.
·
Healy reported
that the construction financing for the Northeast Phase Project matures on February
1, 2003, and it needs to be extended until the project is closed and permanent
financing is provided by USDA-RD. M/S/P
Buysse/Simonson to approve extension of the Minnesota Rural Water Finance
Authority construction loan to September 6, 2004, and to authorize the Chairman
or Vice Chairman and the Secretary or Treasurer to execute the Extension
Certificate and such other documents as are needed to extend the construction
financing.
·
Healy
presented information on the planned December 19th System Tour and
Water Issues Discussion for state and federal elected officials. Senator Arlene Lesewski will be invited and recognized for her
support of LPRW and water issues during her tenure in the Minnesota State Senate.
Committee Reports: The following committee reports were
given:
Executive Committee: Reported via minutes.
Budget & Finance Committee: Reported via minutes.
Personnel Committee: Reported via minutes.
Water Resources and Equipment Committee: No report.
Minnesota Rural Water Association, Board
Representative: Leonard Swenson updated the Board on the
MRWA office project and operations.
Other Business: A Christmas Party is planned for
December 7th. M/S/P
Buysse/Lonneman to provide a ham for each of the employees.
Adjournment:
M/S/P Simonson/Swenson to adjourn the meeting at 4:00 p.m. The next Regular Board meeting will be
Monday, December 30, 2002 at 10:00 a.m.
______________________________________________
Rod Spronk,
Secretary