LINCOLN PIPESTONE RURAL WATER SYSTEM

East Highway 14, P.O. Box 188, Lake Benton, MN 56149

                (507) 368-4248 or (800) 462-0309                 fax (507) 368-4573                                  email:  lprw@itctel.com

 

 

 

 

 

MEETING MINUTES

February 24, 2003

 

 

The regular scheduled meeting of the Lincoln Pipestone Rural Water (LPRW) System Board of Commissioners was held at the LPRW office in Lake Benton on Monday, February 24, 2003 starting at 10:00 a.m.  Chairman Frank Engels called the meeting to order with Commissioners Ken Buysse, Jerry Lonneman, Charlie Simonson, Rod Spronk, Leonard Swenson, Bill Ufkin, Henry Van Dyke, and Joe Weber present. Commissioner Roger Gilliland was absent.  Also present were LPRW Attorney, Dan McDonald; DGR Engineer, John Madden; Field Superintendent, Don Drietz; Director of Operations, Don Evers; and Director of Finance and Administration, Dennis Healy.

 

Agenda:  The Agenda was approved as presented.

 

Minutes:  M/S/P Ufkin/Van Dyke to approve the minutes of the January 27, 2003 Regular Board meeting.

 

Treasurer's Report:  M/S/P Swenson/Lonneman to approve the Treasurer's Report as presented.

 

Bills:  M/S/P Weber/Buysse to approve the following bills for payment:

·   DeWild Grant Reckert and Associates Company: Minneota Tower #30 = $2,082.08; NE Phase #27 = $9,615.84; Lynd Area #26 = $1,227.00; General Services #23 = $1,326.00

·   McDonald, Gudmestad & Schramel: General Legal Services = $909.22

·   Eatherly Constructors, Inc.: NE Phase Schedule 1B Mainline-Pay Estimate #4 = $222,960.29

·   KHC Construction, Inc.: NE Phase Minneota Booster-Pay Estimate #2 = $57,048.50

·   Liesch Associates, Inc.: Well #8 Invoice #7 = $1,178.00; Adrian pump test Invoice #3 = $1,100.36

·   Energy Alternatives: Burr and Verdi Standby Generators = $665.00

·   Wells Fargo Brokerage Services:  Generator Lease Payment #1 = $12,799.15

 

Attorney’s Report:  LPRW Attorney, Dan McDonald reviewed procedures for filling vacancies on the Board, and outlined procedures to be followed.

 

Engineer’s Report:  John Madden reported on the following items:

 

  Lynd Project:  Winter Brothers Underground has completed all work but they need to complete final paperwork.  Engineering America Inc. is done with the Lynd Standpipe and Booster project except for disinfection of the tank that will be done in the spring.  The Booster Station is being used to supply water to the City of Lynd, but the SCADA controls have not been installed yet.  Underground Developers Inc. has completed work on the Schedule 1B Pipeline work, but final cleanup will be done in the spring.

 

  Minneota Tower & Booster Project:  Caldwell Tanks will not be doing additional work on the tower until spring, but KHC is working on the Booster Station portion of the project.

 

   Green Valley Booster Project:  Plans are about ready to be sent to agencies for review.

 

  North Internal Users Project:  The Internal Users Expansion is being kept open until spring for final cleanup and for any additional users added over the winter.

 

 

 

 

 

  Northeast Phase Mainline and User Additions Projects:

 

   Eatherly Constructors, Inc. is completing some work as weather allows.  Quantity and price adjustments are being reviewed in light of contract reductions.  M/S/P Spronk/Van Dyke to approve Change Order #3 to decrease contract quantities on this contract by the equivalent of 100 users and deduct $1,052,345.88 from the contract price.

  GPS Mapping:  GPS mapping of the Northeast Phase project was discussed.  M/S/P Ufkin/Swenson to authorized DGR to work with LPRW staff to complete GPS mapping of all parts of the Northeast Phase Project.  Madden indicated that the engineering costs for the Northeast Phase may be reduced due to the reduction in scope, and that the GPS work is consistent with the work included in the scope of services of the original engineering contract.

 

   John Madden reported that he will be stepping down as President of DGR but that he will remain in an engineering capacity for the foreseeable future.

 

 

Production and Distribution Improvement Issues:

 

  Burr Exploration:   LTP Enterprises completed work on Burr Well #8 pumping test, and the preliminary results look promising at 350 gallons per minute.  The Board directed staff to close out the LTP contact, and begin the process to bid additional work at the Burr WTP. 

 

   Frank Engels, Jerry Lonneman, Joe Weber, Don Evers and Dennis Healy met with the City of Adrian to discuss both short and long range service options.  The Adrian Utilities Commission assured LPRW that they would meet peak demands in 2003 if possible, and LPRW agreed to conduct preliminary exploration activities outside the existing Adrian well field.  Both groups have expressed their desire to continue to cooperate on water issues.

 

   Don Evers reported that he had been contacted about purchasing water from Rock County Rural Water.

 

   The Board decided to explore both the Adrian and Rock County water sources.

 

 

Health Insurance Presentation: Steve Severson representing the Appletree Institute, the Administrator of the BCBS health plan used by LPRW, met with the Board to present a new health insurance option called a VEBA Plan that LPRW may want to consider for next years renewal.  Dennis Healy and Ken Buysse will also be attending a meeting on health insurance and related issues on February 25th.

 

 

Director of Operations Report:

·   Don Drietz reported that the Northeast Phase contractor has been having problems with a tie-in at Green Valley and several outages have resulted.  We are working with the contractor to correct the problem.

·   Don Evers reported that $7 million in federal funding has been approved for the Lewis and Clark Rural Water project.

·   Both the Verdi and Burr generators are working.  Cost estimates for a generator in the Verdi well field were reviewed.

 

Director of Finance and Administration Report:

·   Minnesota Valley Electric Cooperative sent a request for LPRW to appoint a voting delegate for their annual meeting.  M/S/P Lonneman/Weber to appoint Leonard Swenson as the LPRW voting delegate, and to appoint Charlie Simonson as the alternate.

·   Healy presented information on the March 27th LPRW Wellhead Protection meeting to be presented by the University of Minnesota Southwest Research and Outreach Center.  Several Board members and staff will be attending.

·   The Board reviewed a request for matching funds to support a Farm Bill Assistance Grant for the Pipestone County SWCD.  M/S/P Lonneman/Weber to provide up to $3,500 in matching funds for the project.

·   Health reported that grant funds for security measures may be available through Lincoln County and perhaps other surrounding counties.

·   Healy updated the Board on the agenda at the MRWA Conference.

 

 

 

Committee Reports: The following committee reports were given:

Executive Committee: No report.

Budget & Finance Committee: No report.

Personnel Committee: No report.  The Personnel Committee will meet at 1:00 p.m. on March 21st.

Search Committee: No report.

Water Resources and Equipment Committee: No report.  M/S/P Ufkin/Buysse to authorize the Water Resources & Equipment Committee to take care of all farm program matters for LPRW property, and to give Don Evers Power Of Attorney to sign for all farm program matters.

Minnesota Rural Water Association, Board Representative:  Leonard Swenson updated the Board on MRWA activities.

 

Other Business:  Possible requests to manage small sewer systems on area lakes were discussed, and will be considered when more information is known.  The Search Committee will meet on March 21st if information can be received soon enough.

 

Adjournment:  M/S/P Lonneman/Spronk to adjourn the meeting at 4:30 p.m.  The next Regular Board meeting will be Monday, March 31, 2003 at 10:00 a.m.

 

 

 

 

 

 

 

 

 

                                                                                     ______________________________________________

                                                                                                Rod Spronk, Secretary