LINCOLN PIPESTONE RURAL WATER SYSTEM
East Highway 14, P.O. Box 188, Lake Benton, MN
56149
(507)
368-4248 or (800) 462-0309 fax
(507) 368-4573 email: lprw@itctel.com
MEETING MINUTES
August 25, 2003
The regular scheduled meeting of the
Lincoln Pipestone Rural Water (LPRW) System Board of Commissioners was held at
the LPRW office in Lake Benton on Monday, August 25, 2003 starting at 6:00
p.m. Chairman Frank Engels called the meeting to order with
Commissioners Ken Buysse, Earl DeWilde, Charlie Simonson, Rod Spronk, Leonard Swenson, Henry Van Dyke, Joe
Weber, and Bill Ufkin present. Commissioner Jerry Lonneman was
absent. Also present were LPRW Attorney, Dan McDonald; DGR Engineer, John Madden; Field Superintendents, Don Drietz and
Tom Muller; Director of Finance and Administration, Dennis Healy; and Director
of Operations, Don Evers.
Agenda:
The Agenda was approved as presented.
Minutes:
M/S/P Ufkin/Van Dyke to approve the minutes of the July 28, 2003 Regular
Board meeting.
Treasurer's Report:
M/S/P Buysse/Swenson to approve the Treasurer’s report as presented.
Bills:
M/S/P Weber/Simonson to approve the following bills for payment:
· DeWild Grant Reckert and
Associates Company: Minneota Tower #36 = $1,695.09; NE Phase #33 = $14,606.15;
Lynd Area #32 = $773.00; General Services #29 = $156.00
· McDonald, Gudmestad
& Schramel: General Legal Services = $868.87; Northeast Expansion = $140.00
· Eatherly Constructors, Inc.: NE Phase
Schedule 1B Mainline-Pay Estimate #10 = $279,061.68
· Caldwell Tanks, Inc.: NE Phase Minneota
Tower-Pay Estimate #7 = $35,625.00
· Robert L. Carr Co.: NE Phase Green Valley
Booster-Pay Estimate #1 = $11,875.00
Attorney’s Report: Appointment
of a new Board member from the Northeast Expansion area was discussed, and
Search Committee recommendations were reviewed. Dan McDonald reviewed appointment procedures with the
Board. The Board instructed Healy to
send letters to the list prepared by the Search Committee to invite them to
submit a letter of application if they are interested in the appointment.
Engineer’s Report: John
Madden reported on the following items:
• Schedule 1B Mainline:
The contractor is installing services, and people are beginning to receive water. M/S/P Van Dyke/Simonson to approve, subject to USDA-RD concurrence,
Change Order #6 increasing the Eatherly Contract by $31,771.00 for the Burr
Well pipeline and mag meters at Hazel Run and Echo.
• Green Valley Booster:
Work has started on the project, and the booster should be delivered in October.
• Burr Wells: The Ervin Well Company is ready to start
work pending final approval by MDH. M/S/P
Weber/Swenson to approve, subject to USDA-RD concurrence, Change Order #1
increasing the Ervin Well Company Contract by $34,123.74 for stainless steel
drop pipe in wells 8, 9 & 10.
• Lynd Project:
The Project is complete except for some minor cleanup and paperwork.
• Minneota Tower and Booster:
Painting of the tower should be completed by mid-September. KHC is taking care of paint problems for the
booster station portion of the project.
• Burr WTP Improvement: The
preliminary engineering report for the project is being prepared.
Regional Water
Development:
• Adrian: Jerry Lonneman and LPRW staff met with a landowner in
the Adrian area to discuss purchase of a well site, and the landowner is
reviewing our offer.
• Edgerton Well: The
well is not being used now, and treatment options to deal with iron problems
are being reviewed.
• City of Dawson: The Board decided to begin feasibility
studies this winter.
Director of Operations
Report:
· Don Evers reported that Lewis & Clark
groundbreaking was successful, and work has begun on the project.
· M/S/P Weber/Ufkin to authorize Energy
Alternatives to proceed with design and installation of a standby generator at
the Verdi Well Field based on their estimated cost of $83,000.
· Don Drietz reported that operations were
going smoothly, and pipeline relocation is being done as part of a highway
project near Minneota.
· Tom Muller reported that Jeff Dale of
MRWA did pressure testing at Woodstock and LPRW pressure were found to be good,
but some valves in town were partially closed resulting in some pressure
problems.
Director of Finance and
Administration Report:
· The Minnesota Senate Bonding Committee
will be meeting in Luverne on September 9th and Board members are
encouraged to attend if possible.
· A summary of hookups in the Northeast
Phase Expansion Project was presented for Board review.
· Health Insurance costs are scheduled to
increase by 6.7% in 2004. This is the
lowest increase in our group.
· Healy reported that the cost of DNR
Stream Crossing Permits has increased from $40 to $500 per crossing. For the Northeast Phase that would have
increased the project cost from approximately $2,000 to approximately
$25,000. The Board directed Healy to
pass this information on to our elected representatives.
Committee Reports: The following committee reports were
given:
Executive Committee: No report.
Budget & Finance Committee: The Committee will meet before the next
Board meeting if possible.
Personnel Committee: The Committee will meet
at 6:00 p.m. on September 11th at the LPRW office.
Search Committee: The Committee met at the Corner Café in
Taunton at 7:30 p.m. on Wednesday, August 13th
Water Resources and Equipment Committee: No report.
Minnesota Rural Water Association, Board
Representative: Leonard Swenson reported on the last MRWA meeting.
Adjournment:
M/S/P Swenson/Weber to adjourn the meeting at 9:30 p.m. The next Regular Board meeting will be
Monday, September 29, 2003 at 6:00 p.m.
______________________________________________
Rod
Spronk, Secretary