LINCOLN PIPESTONE RURAL WATER SYSTEM
East Highway 14, P.O. Box 188, Lake Benton, MN
56149
(507)
368-4248 or (800) 462-0309 fax
(507) 368-4573 email: lprw@itctel.com
MEETING MINUTES
October 25, 2004
The regular scheduled meeting of the
Lincoln Pipestone Rural Water (LPRW) System Board of Commissioners was held at
the LPRW office in Lake Benton on Monday, October 25, 2004 starting at 6:00
p.m. Chairman Rod Spronk called the meeting to order with
Commissioners Mike Brunner, Ken Buysse, Earl DeWilde, Frank Engels, Charlie Simonson, Leonard Swenson, Joe
Weber, Jerry Lonneman, Henry Van Dyke, and Bill Ufkin present. Also present were Bob Eatherly,
Eatherly Constructors, Inc.; Board Attorney, Ron Schramel; DGR Engineer Darin Schriever; Field Superintendent Don Drietz;
Director of Finance and Administration, Dennis Healy; and Director of
Operations, Don Evers.
Agenda:
M/S/P Engels/Lonneman to approve the Agenda with the addition of several
items.
Minutes:
M/S/P Engels/Brunner to approve the minutes of the September 27, 2004
Regular Board meeting.
Treasurer's Report:
M/S/P Lonneman/Buysse to approve the Treasurer’s report as presented.
Bills:
M/S/P Swenson/Engels to approve the following bills for payment:
· DeWild Grant Reckert and
Associates Company: NE Phase #47 = $15,468.66; Lismore Service Connection #3 =
$1,000.00; General Services #40 = $1,456.50
· McDonald, Gudmestad
& Schramel: General Legal Services = $1,413.00; NE Expansion = $84.00
· Pat Sterzinger: (NE Phase) Schedule
1C-Pipeline Extensions, PPE#3 = $113,050.84
· Prairie Wild Enterprises, Inc.: (NE
Phase) Minneota storage building hydro seeding = $1,298.77
· Liesch Associates, Inc.: (Adrian) Adrian
well # 7 = $1,032.00
· US Bank: 1997 Refunding Bond payment =
$289,377.50
Bonds:
M/S/P Engels/Simonson to authorize the LPRW staff and The PFM Group to
proceed with refinancing of the “General Obligation Refunding Bonds of 1998
Series B” issued through Lincoln County provided that adequate savings can be
achieved. M/S/P Lonneman/Brunner to authorize the LPRW staff to proceed to
prepay the “General Obligation Refunding Bonds of 1998” issued through Lincoln
County.
Attorney’s Report: Board Attorney, Ron Schramel presented a
“Legal Services Agreement” for the USDA-RD System-wide Expansion and
Improvement Project for Board consideration.
M/S/P DeWilde/Swenson to approve the “Legal Services Agreement” with
McDonald Gudmestad & Schramel, PLLP for the System-wide Expansion and
Improvement Project.
Lismore:
Mid States is close to completing the work on the Lismore hookup. M/S/P Buysse/Van Dyke to approve Change
Order #1 that extends the completion date by 15 days.
Engineer’s Report: Darin Schriever reported on the following items:
• Schedule 1B Mainline: Bob Eatherly representing Eatherly
Constructors, Inc. met with the Board to discuss issues relating to the
closeout of the Schedule 1B Mainline contract.
The Board expressed their desire to closeout the project, but a number
of punch list items need to be completed.
Bob Eatherly said he will have people here for the next 2 or 3 to complete
the punch list items, and he will provide the Board a proposal to settle the
final quantity issues by November 15th. M/S/P Lonneman/DeWilde to direct the LPRW staff to hire someone
to finish the punch list items if Eatherly does not complete them by November
15th. All cost will be
billed back to Eatherly and/or his bonding company.
• GIS/GPS:
DGR is about 90% done with the staking sheets.
• Schedule 1C Pipeline:
The contractor is making satisfactory progress. M/S/P Weber/Lonneman to approve Change Order
No. 2 to the contract for Northeast Phase and Internal Expansion Schedule 1C –
Pipeline Extensions to increase the contract by $5,319.56, and to add 15 days
to the contract completion.
• Burr WTP Improvements:
Work on the treatment plant projects is progressing, and much of it will
be ready for final payment at the November meeting.
• Burr GSR: USDA-RD is reviewing
the Preliminary Engineering Report.
• 2005
Project Application: The 2005-2008
System-wide Expansion and Improvement Project is being processed by USDA-Rural
Development.
• Adrian:
DGR is working on plans to connect the well to the City system after the
well is drilled. Liesch Associates has submitted well plans to the Minnesota
Department of Health for approval.
Regional Water Development:
• Lewis and Clark:
Construction and design work continues on the project.
• Edgerton:
No new information on the City of Edgerton interconnect.
Director of Operations
Report: Don Evers reported on the following
items:
• CRP
issues with the Pipestone County FSA office were discussed.
·
The Lewis
& Clark project report was presented.
·
Small
booster pumps are needed at the Chandler tower and south of the Ivanhoe
tower. M/S/P Lonneman/Van Dyke to
install both booster pumps this fall if possible.
·
Evers
requested authorization to purchase a semi-tractor and trailer to replace the
1987 gravel truck and trailer. The
purchase was included in the 2004 Capital Improvement Program at a net cost of
$45,000. M/S/P Ufkin/Lonneman to
authorize staff to purchase a semi-tractor and trailer at a net cost not to
exceed $45,000.
Director of Finance and
Administration Report:
·
The
Northeast Phase Project financial status was reviewed.
Committee Reports: The following committee reports were
given:
Executive Committee: No report.
Water Resources and Equipment Committee: No report.
Personnel Committee: No report.
Budget & Finance Committee:
No report.
Minnesota Rural Water Association, Board
Representative: Leonard Swenson updated the Board on MRWA activities
including the new vehicle purchase program.
Adjournment:
M/S/P Engels/Lonneman to adjourn the meeting at 10:15 p.m. The next Regular Board meeting will be
Monday, November 29, 2004 at 10:00 a.m.
______________________________________________
Joseph Weber, Secretary